[bind10-dev] [sprint planning] estimates for sprint ending 2011-11-08
JINMEI Tatuya / 神明達哉
jinmei at isc.org
Tue Oct 25 06:13:42 UTC 2011
At Sun, 23 Oct 2011 14:22:06 +0200,
Jelte Jansen <jelte at isc.org> wrote:
> as promised (well, almost, I promised i'd do this on saturday, but it
> was suddenly sunday already), here is the list of tickets from the
> proposed queue that have no estimation yet. I also added a few with
> status new from the current sprint (the nsec support ones).
I just sent my estimates unicasted to you. While I also gave points
to the NSEC support ones, I'd note that there's a parent ticket of
these (#1244, with quite a large estimate point), and the completed
children weren't given estimate points.
So, simply giving estimates to the remaining children is probably not
the best way. We should either:
- leave children's estimates blank (and consider the parent task a
minimum unit in terms of estimates/progress management
- reduce the estimate point of the parent and give all children
(including the completed one) estimates
---
JINMEI, Tatuya