[bind10-dev] Estimates for current sprint - results

Stephen Morris stephen at isc.org
Tue Sep 6 17:00:10 UTC 2011


On 06/09/2011 17:34, JINMEI Tatuya / 神明達哉 wrote:
> At Tue, 06 Sep 2011 13:33:41 +0100, Stephen Morris
> <stephen at isc.org> wrote:
> 
>> These are the estimates for tasks in the current sprint (thanks
>> to Stephen, Michal and Jelte) plus the value I've chosen for the
>> consensus. The "Estimated Difficulty" values in Trac have been
>> updated.
> 
> Hmm, I thought I sent my estimates on Aug 26.  I've copied my 
> estimates below for reference.  Most of them are consistent with
> the "consensus", but I guess we should increase them for #1177 and
> #1178 to something like "5".

You did, my apologies.  I missed it in the email backlog.

I've adjusted the estimates for 1177 and 1178.

Stephen



More information about the bind10-dev mailing list