[bind10-dev] [sprint planning] estimates for sprint ending 2012-02-21

JINMEI Tatuya / 神明達哉 jinmei at isc.org
Mon Feb 6 01:41:37 UTC 2012


At Sun, 05 Feb 2012 21:01:46 +0100,
Jelte Jansen <jelte at isc.org> wrote:

> See attachment, I've moved a number of tickets that sounded important
> or interesting from the new tasks to next-sprint-proposed, but the
> decision process can probably be quite accurately categorised as
> 'arbitrary'.
> 
> Please have the results back on my virtual desk by tuesday start of
> business (i.e. at 0800 UTC)

I missed this message when I added a few more tickets, some of which
were not given estimates.  In case it's not too late I've revised the
CSV file so it includes the additional tasks.  It would be nicer if
others can fill in this version.

> ps. I also moved a number of nsec3 related tasks to *this* sprint, so
> that we don't run out of items on monday, these are tasks 1580-1586.

I also missed this and accidentally moved them to the
next-sprint-proposed queue.  I've moved them back to the current
sprint queue again.

---
JINMEI, Tatuya

-------------- next part --------------
A non-text attachment was scrubbed...
Name: estimates-sprint-20120221.csv
Type: application/octet-stream
Size: 1077 bytes
Desc: not available
URL: <https://lists.isc.org/pipermail/bind10-dev/attachments/20120205/dcf340f8/attachment.obj>