[bind10-dev] Year 4 resolver goals
Shane Kerr
shane at isc.org
Thu Mar 22 15:16:46 UTC 2012
All,
I've put together a set of goals regarding the resolver work in year 4.
This is similar to the ones for usability that went out some weeks ago.
We have a text file explaining a little bit about each focus area, and
then a spreadsheet with some numbers in Open Document Spreadsheet (ODS)
format as well a corresponding comma-separated-variable (CSV) file. The
spreadsheet contains rough estimates on my part on how long it would
take for 1 engineer to finish the job.
Note that I've italicized some goals that I think can be postponed for
now, such as source IP (not port) randomization, collecting ICMP
unreachable responses, and so on.
We have less flexibility here than with the usability work, I think.
Given the amount of work here, it is likely to take the entire rest of
year 4, after we finish our usability work.
Please have a look, and send feedback.
Thanks,
--
Shane
-------------- next part --------------
An embedded and charset-unspecified text was scrubbed...
Name: resolver-goals.txt
URL: <https://lists.isc.org/pipermail/bind10-dev/attachments/20120322/877a0451/attachment.txt>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: resolver-goals-estimates.ods
Type: application/vnd.oasis.opendocument.spreadsheet
Size: 12013 bytes
Desc: not available
URL: <https://lists.isc.org/pipermail/bind10-dev/attachments/20120322/877a0451/attachment.bin>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: resolver-goals-estimates.csv
Type: text/csv
Size: 2652 bytes
Desc: not available
URL: <https://lists.isc.org/pipermail/bind10-dev/attachments/20120322/877a0451/attachment-0001.bin>
More information about the bind10-dev
mailing list