[bind10-dev] including estimated load of carried-over tasks
JINMEI Tatuya / 神明達哉
jinmei at isc.org
Tue Dec 6 17:50:14 UTC 2011
We briefly discussed taking into account the estimated points of tasks
when they are not completed in a single sprint and carried over to the
next one. I think it makes sense, and this is a tentative proposal
for that:
- We include 100% of the estimated points of non assigned tasks (which
we already do?)
- We include 50% of the estimated points of assigned but not in review
tasks
- We include 25% of the estimated points of tasks being reviewed
---
JINMEI, Tatuya