[bind10-dev] R-Team Sprint Planning Meeting 25 Jan 2011

Stephen Morris stephen at isc.org
Tue Jan 25 16:12:58 UTC 2011


Following the R-Team sprint planning session today:

* A new sprint milestone has been created (http://bind10.isc.org/milestone/R-Team-Sprint-20110208) and all tasks not marked as complete have been moved to it.  This has also been marked as the "Current R-Team Sprint" on the "Sprint Progress" page (http://bind10.isc.org/wiki/SprintProgress).

* An R-Team task backlog milestone has been created (http://bind10.isc.org/milestone/R-Team-Task-Backlog).  If you identify any additional tasks for the resolver, please create them and add them to this page.  We'll discuss them (and maybe estimate them as well) at the next sprint planning session.

* A page has been created to hold notes on the resolver refactoring (http://bind10.isc.org/wiki/ResolverRefactorNotes).

Stephen