[bind10-dev] [sprint planning] estimate results for sprint ending 2012-03-06
JINMEI Tatuya / 神明達哉
jinmei at isc.org
Wed Feb 22 19:37:37 UTC 2012
At Wed, 22 Feb 2012 11:18:28 +0100,
Shane Kerr <shane at isc.org> wrote:
> > > Also, one list of estimations is quite out of tune with the rest.
> > > Since I had 7 sets of data to average out this doesn't influence it
> > > too much, but you might want to check your calculation method :)
> >
> > I see many two-digit points in one column. I guess it's from someone
> > not so familiar with the implementation, and if so, giving higher
> > numbers basically makes sense. Yet I think it would be nicer if we
> > had a more consistent feeling about the meaning of the numbers -
> > consider an extreme case where someone gives over 1000 points to all
> > items. Obviously it won't work any more.
>
> I suspect the problem may be that the column says 'estimated hours',
> which isn't really the meaning, right?
Correct, it's not hours (whether we should give estimates in actual
time or relative points is another question, though. I've read a book
about agile-style planning that recommends making short time
estimations by actual hours).
---
JINMEI, Tatuya