[bind10-dev] [sprint planning] estimate results for sprint ending 2012-03-06
Shane Kerr
shane at isc.org
Wed Feb 22 10:18:28 UTC 2012
Jinmei,
On Tuesday, 2012-02-21 09:54:20 -0800,
JINMEI Tatuya / 神明達哉 <jinmei at isc.org> wrote:
> At Tue, 21 Feb 2012 12:12:35 +0100,
> Jelte Jansen <jelte at isc.org> wrote:
>
> > As usual, the usual suspects provided a few small comments, added to
> > the last two columns.
> >
> > Also, one list of estimations is quite out of tune with the rest.
> > Since I had 7 sets of data to average out this doesn't influence it
> > too much, but you might want to check your calculation method :)
>
> I see many two-digit points in one column. I guess it's from someone
> not so familiar with the implementation, and if so, giving higher
> numbers basically makes sense. Yet I think it would be nicer if we
> had a more consistent feeling about the meaning of the numbers -
> consider an extreme case where someone gives over 1000 points to all
> items. Obviously it won't work any more.
I suspect the problem may be that the column says 'estimated hours',
which isn't really the meaning, right?
> So it would be useful if we had some hint about how to give estimate
> points on a wiki page.
Yes, agreed. I've created ticket #1699 for this and put it in the
non-development-work queue.
https://bind10.isc.org/ticket/1699
Cheers,
--
Shane
More information about the bind10-dev
mailing list