[bind10-dev] statistics plan
Naoki Kambe
kambe at jprs.co.jp
Mon Jul 23 09:10:12 UTC 2012
Hello,
We JPRS developers have planned on statistics tasks as I attached a
gantt chart on this mail. Our goal is to finish all of what we agreed
on statistics in the last f2f meeting until the beta release upcoming
in Sept.:
http://bind10.isc.org/wiki/April2012MeetingMinutes#Estimates.
We must work hard for accomplishing it.
The chart shows a task in each ticket. That is, it shows when status
of ticket will be reviewing and which sprint the task will be finished
at. Can we ask someone than JPRS to review when working is done? We
have roughly estimated how much we will work on each ticket. These
lines are based on that. More tickets are scheduled in latter sprints
but we have considered cost of revising due to feedback of reviewing.
We'll create unpublished tickets before estimation timing for the next
sprint.
If you have any comments to this plan, please let me know.
From: JINMEI Tatuya / 神明達哉 <jinmei at isc.org>
Date: Thu, 19 Jul 2012 11:52:22 -0700
> Does this include supporting per-zone statistics for a very large
> number of zones (like millions)? If so, that would be very cool.
Of course, we have considered tasks on per-zone statistics too but I
think we need to carefully measure for knowing how many numbers of
zones can be supported. :)
Thanks,
Naoki Kambe
-------------- next part --------------
A non-text attachment was scrubbed...
Name: bind10_statistics_plan.pdf
Type: application/pdf
Size: 46718 bytes
Desc: not available
URL: <https://lists.isc.org/pipermail/bind10-dev/attachments/20120723/e49f00b9/attachment-0001.pdf>
More information about the bind10-dev
mailing list